Meter exchange procedure

Reader group: Field crews
In a live knowledge base, only signed-in field crew members would see this page. It's public in this demo so you can explore.
  1. Before you go: check the work order for a medical priority flag. If flagged, call the customer first.
  2. At the door: follow Customer contact at the door.
  3. Inspect: look for meter base damage, signs of tampering or heat discoloration. If you find any, stop and report it.
  4. PPE: arc-rated face shield, gloves and clothing rated for the meter base.
  5. Read and photograph the old meter.
  6. Exchange the meter, check the seal, and confirm the new meter powers on and communicates.
  7. Close out: record both meter numbers and readings, and leave a door hanger.

Never pull a meter on a solar home until you've confirmed the inverter is off.